As Adjoining Owner’s surveyor our concern was that our client’s property and the occupying staff were fully protected before commencement of a major demolition and new development project that also involved deep piling. Together with the Building Owner’s surveyor a detailed schedule of condition of all internal walls, external elevations and the roof within 6 metres of their building were completed.
Discussions are in progress to mitigate the noise, dust and vibration that will arise so that the quiet enjoyment of staff continues without significant compromise.